Water Infrastructure Grants Guide: SRFs, WIFIA & IIJA

Updated 19 official sources

Quick Answer: The IIJA invested $55 billion in water infrastructure, the largest federal investment ever.

Full answer and how we checked it

This guide is for water utilities, local governments, tribes, state infrastructure offices, rural systems, and engineering teams deciding between SRF, WIFIA, USDA, IHS, and Army Corps routes. The Clean Water SRF received $11.7 billion, the Drinking Water SRF got $11.7 billion plus $15 billion for lead pipe replacement, and $10 billion targets PFAS and other emerging contaminants ($5 billion EC-SDC grants, $4 billion DWSRF, $1 billion CWSRF). These funds flow through state agencies, not direct federal applications. FY2026, which ended September 30, 2026, was the last year of IIJA advance appropriations; states are still deploying the money.

Data note: Unless labeled otherwise, funding amounts are multi-year IIJA (FY2022-2026) totals from the EPA, HHS, and Congressional Research Service sources linked in each section.

In this guide

If you're a water utility, local government, or tribal community dealing with aging pipes, contamination, or capacity limits, this guide covers every major funding source available.

America's water infrastructure carries a price tag that's hard to overstate. EPA estimates the nation needs $625 billion in drinking water infrastructure investments over the next 20 years, according to its 7th Drinking Water Infrastructure Needs Survey (opens in a new tab), and $630.1 billion in clean water needs, according to the 2022 Clean Watersheds Needs Survey (opens in a new tab). The American Society of Civil Engineers' 2025 Report Card gives drinking water a C- and wastewater a D+. And there are an estimated 4 million lead service lines still in use, according to EPA (opens in a new tab).

The Bipartisan Infrastructure Law responded with $55 billion for water, the largest federal water investment ever. But here's what makes water funding different from other federal grants: almost none of it goes directly from Washington to your community. It flows through your state first. Understanding how that state-level distribution works is the difference between getting funded and getting left on a waiting list.

Water infrastructure is one of the most complex funding flows in government. This guide covers every major program, how the state pipeline actually works, who's eligible, and how to position your community for funding.


Get grant deadline alerts by email

About once a week, we email a short list of open grant calls with real deadlines from different funders. It isn't limited to the programs in this guide.

No spam. Unsubscribe anytime.

How Water Infrastructure Funding Works: The State Pipeline

Before getting into specific programs, you need to understand the basic funding flow, because it's different from almost every other federal grant.

For most federal grants, you apply directly to the federal agency. For water infrastructure, you apply to your state. Here's why:

Step 1: Congress appropriates money to EPA for the State Revolving Fund programs.

Step 2: EPA distributes capitalization grants to each state based on a needs-based formula derived from the quadrennial Drinking Water Infrastructure Needs Survey and Assessment.

Step 3: Each state matches EPA's base capitalization grant at 20%. For the BIL general supplemental funds, the state match was 10% in FY2022 and FY2023 and rose to 20% from FY2024, according to EPA's FY2024 SRF allotments memo (opens in a new tab). Only the BIL lead service line and emerging contaminants funds have no state match.

Step 4: Your state's SRF program maintains a priority list (sometimes called an Intended Use Plan or IUP) that ranks eligible projects by environmental and public health need.

Step 5: You apply to your state SRF program, which reviews your project, ranks it on the priority list, and offers financing if your project scores high enough.

Step 6: As borrowers repay their loans, the money revolves back into the fund for future projects.

This means your first call should always be to your state's drinking water or clean water finance agency, not to EPA. The EPA water infrastructure page (opens in a new tab) lists contact information for every state SRF program.

Clean Water State Revolving Fund (CWSRF)

The CWSRF is EPA's largest water funding program by dollar volume. It finances wastewater treatment plants, stormwater management systems, nonpoint source pollution projects, and estuary protection.

Base Funding Plus IIJA

EPA's base CWSRF capitalization is approximately $1.64 billion per year. The Bipartisan Infrastructure Law added $11.7 billion over five years (FY2022-FY2026), bringing total available federal capitalization to approximately $3.5 billion per year during peak BIL years, according to EPA's IIJA resources page (opens in a new tab).

The BIL also added a separate $1 billion over five years for emerging contaminants (PFAS and similar) through the CWSRF.

Who's Eligible

Only states receive EPA's capitalization grants directly. States then lend to:

  • Municipalities and counties
  • Special-purpose districts (sanitation districts, water authorities)
  • Tribal communities
  • In some states, private water and wastewater systems

Loan Terms

  • Interest rates: Typically 0% to 2%, well below municipal bond market rates
  • Repayment terms: Up to 30 years (40 years for some disadvantaged communities)
  • Principal forgiveness: Under the BIL, 49% of supplemental SRF funds must be distributed as principal forgiveness or grants to disadvantaged communities. This effectively converts half of the BIL's water investment from loans to grants.

What It Funds

Eligible projects include wastewater treatment plant construction and upgrades, sewer system rehabilitation, combined sewer overflow correction, stormwater management infrastructure, nonpoint source pollution control, water reuse projects, and energy efficiency improvements at treatment facilities.

How to Apply

Contact your state's clean water SRF program. Each state has its own application timeline, typically tied to an annual or biannual Intended Use Plan cycle. Your state ranks projects using criteria that generally include:

  • Public health impact: Projects addressing documented health risks score higher
  • Regulatory compliance: Projects needed to meet EPA discharge permits or consent decrees
  • Environmental benefit: Measured reduction in pollutant loading
  • Community need: Disadvantaged communities receive scoring preferences under BIL requirements
  • Project readiness: Projects that can begin construction quickly score higher, especially now that the final IIJA tranche has been appropriated

Practical tip: Get on your state's priority list as early as possible, even if your project isn't fully designed. Many states allow "planning-level" entries that establish your place in line. Design and engineering costs are often eligible for SRF financing, so you can use SRF funds to develop your project.

Drinking Water State Revolving Fund (DWSRF)

The DWSRF operates similarly to the CWSRF but focuses on drinking water systems. The IIJA significantly expanded this program with both general funding and dedicated set-asides.

Funding Breakdown

  • Base DWSRF capitalization: Approximately $1.13 billion per year
  • BIL supplemental DWSRF: $11.7 billion over five years (FY2022-FY2026)
  • Lead service line replacement set-aside: $15 billion over five years (FY2022-FY2026)
  • Emerging contaminants (PFAS): $4 billion through the DWSRF emerging contaminants supplemental, plus $5 billion through the separate Emerging Contaminants in Small or Disadvantaged Communities grant program

According to EPA's DWSRF page (opens in a new tab), total federal investment in the DWSRF through the BIL exceeds $30 billion, more than tripling the historical program size.

Eligible Projects

  • Water treatment plant construction and upgrades
  • Transmission and distribution system replacement
  • Source water protection
  • Storage facility construction
  • Lead service line replacement
  • PFAS and emerging contaminant treatment
  • Water system security improvements

Lead Service Line Replacement: $15 Billion

The IIJA's lead pipe funding is the largest targeted investment in lead remediation in history. EPA allocates $3 billion per year to states specifically for lead service line replacement, per the Congressional Research Service (opens in a new tab).

Key features:

  • No state match requirement for lead set-aside funds
  • 49% must be provided as principal forgiveness or grants
  • Funds cover identification, planning, design, and replacement of lead lines
  • Both the utility-owned and customer-owned portions of the service line are eligible

2026 update: EPA's 7th Drinking Water Infrastructure Needs Survey (opens in a new tab) now estimates about 4 million lead service lines nationwide, down from the earlier estimate of about 9 million. EPA used the new survey for its FY2025 and FY2026 lead service line allotments, which changed how much each state receives.

How to access it: Apply through your state's DWSRF program. Many states have created dedicated lead service line replacement programs within their SRF structure. Contact your state drinking water agency for the current application process and priority criteria.

PFAS and Emerging Contaminants Funding: $10 Billion Over Five Years

PFAS contamination is one of the fastest-growing water infrastructure challenges, and the IIJA created dedicated funding streams to address it.

Emerging Contaminants in Small or Disadvantaged Communities (EC-SDC) Grant

This is the most direct PFAS funding path. The BIL provides $1 billion per year for FY2022-2026 ($5 billion total) specifically for PFAS testing and treatment in small or disadvantaged communities, according to EPA (opens in a new tab).

Key features:

  • No cost share required. This is 100% federal funding.
  • Non-competitive. States receive allocations based on a formula, then distribute to eligible communities.
  • Who's eligible: Public water systems serving small communities (under 10,000 population) or disadvantaged communities as defined by the state.
  • What it covers: PFAS testing, treatment technology installation, water quality monitoring, and technical assistance.

CWSRF Emerging Contaminants Set-Aside ($1 Billion)

An additional $1 billion over five years (FY2022-2026) flows through the CWSRF specifically for emerging contaminants in wastewater and stormwater systems. States administer these funds through their clean water SRF programs.

How to Access PFAS Funding

  1. Contact your state drinking water agency to determine which PFAS funding streams are available in your state
  2. Conduct PFAS sampling if you haven't already; many states offer free or subsidized testing
  3. Submit a project to your state's SRF priority list or EC-SDC program
  4. States prioritize communities with documented PFAS contamination above EPA's Maximum Contaminant Levels (MCLs), which were finalized at 4 parts per trillion for PFOA and PFOS

WIFIA: EPA's Direct Loan Program for Large Projects

The Water Infrastructure Finance and Innovation Act program is the exception to the "everything goes through states" rule. WIFIA provides low-interest loans directly from EPA headquarters to borrowers for large water projects, according to EPA's WIFIA page (opens in a new tab).

How WIFIA Is Different

FeatureSRFWIFIA
Administered byState agenciesEPA headquarters
Project minimumNo minimum$20M ($5M for small communities)
Max federal shareVaries by state49% (80% for small communities)
Repayment termUp to 30 yearsUp to 35 years after substantial completion
Repayment deferralVariesUp to 5 years after completion
Interest rate0-2% typicallyU.S. Treasury rate (currently ~4%)

Funding Available

In its FY2025 notices of funding availability, EPA announced $6.5 billion in WIFIA lending capacity, with an additional $550 million available to state infrastructure financing authorities through SWIFIA, according to EPA's WIFIA available funding page (opens in a new tab).

Who Should Consider WIFIA

WIFIA works best for:

  • Large projects ($20 million or more) that exceed your state SRF's capacity
  • Projects that need flexible repayment terms
  • Borrowers with strong credit ratings that can get favorable terms
  • Projects combining multiple funding sources (WIFIA can supplement SRF loans)

Application Process

WIFIA uses a two-step process:

Step 1: Letter of Interest (LOI). Submit an LOI describing your project fundamentals and addressing WIFIA selection criteria. EPA reviews for eligibility, creditworthiness, engineering feasibility, and selection criteria alignment. Contact wifia@epa.gov for SharePoint access to submit.

Step 2: Invitation to Apply. If your LOI is selected, EPA invites you to submit a full application with detailed financial, engineering, and environmental documentation. WIFIA operates on a rolling basis, so there's no single annual deadline.

For more on federal infrastructure funding timelines, see our infrastructure grants guide.

USDA Rural Water and Waste Disposal Program

USDA Rural Development operates the federal government's primary water infrastructure program for small rural communities. Unlike the SRF, USDA provides both direct loans and grants, and you apply directly to USDA, not through a state agency, per USDA Rural Development (opens in a new tab).

Program Details

  • Eligible communities: Rural areas and towns with populations of 10,000 or fewer
  • Eligible applicants: Public bodies (municipalities, counties, special districts), nonprofit organizations, and tribal nations
  • Grant amounts: USDA sets grant amounts based on community median household income and project cost. Higher-poverty communities receive larger grant percentages.
  • Loan terms: Up to 40 years at interest rates tied to market conditions, with subsidized rates for low-income communities
  • What it funds: Drinking water systems, wastewater collection and treatment, stormwater drainage, and solid waste disposal facilities

How to Apply

Applications go through your USDA Rural Development state office using the RD Apply system. You'll need:

  • A preliminary engineering report
  • An environmental review
  • Financial projections showing the system can sustain operations through user fees
  • Evidence of community support
  • Documentation that other funding sources (state SRF, commercial financing) are not available at reasonable terms

USDA water projects typically take 18-36 months from application to construction start. Start early.

Rural Decentralized Water Systems Grant

A separate USDA program provides grants to qualified nonprofits to create revolving loan funds or sub-grant programs for individual homeowners needing water and wastewater services. Check the current USDA notice for the match requirement and application window.

Indian Health Service: $3.5 Billion for Tribal Water

The IHS Sanitation Facilities Construction Program received $3.5 billion through the IIJA (FY2022-2026), with $700 million allocated per fiscal year, according to HHS (opens in a new tab).

What it funds: Drinking water supply systems, sewage disposal systems, and solid waste disposal facilities serving Indian homes and communities.

Who's eligible: Federally recognized tribal nations and Alaska Native communities.

How it works: IHS doesn't operate as a traditional grant program. The IHS Sanitation Facilities Construction Program works with tribal communities to identify water and sanitation deficiencies, design systems, and construct facilities. Tribes work with their IHS Area Office to get projects onto the Sanitation Deficiency System (SDS) priority list.

Scale of need: The IIJA money is large, but the backlog of documented sanitation deficiencies is larger. Ask your IHS Area Office where your project sits on the Sanitation Deficiency System list.

EPA Tribal Set-Aside Programs

In addition to IHS, EPA provides direct funding to tribal nations through set-asides within both the CWSRF and DWSRF:

These are true grants, not loans, and they go directly to tribes from EPA (not through states). For more on tribal funding options, see our grants for Native American tribes guide.

Army Corps of Engineers Water Projects

The U.S. Army Corps of Engineers received $17.1 billion through the IIJA for water-related civil works projects, according to the Congressional Research Service (opens in a new tab).

What it funds:

  • Flood risk management (coastal and inland)
  • Navigation and waterway improvements
  • Aquatic ecosystem restoration
  • Water supply infrastructure (reservoirs and conveyance)
  • Shore protection

How it works: Corps projects are different from other water programs. Most are congressionally authorized, meaning Congress directs the Corps to study and potentially construct specific projects. Communities don't apply to the Corps the way they apply to a state SRF. Instead, they work with their Congressional delegation to get projects authorized and funded.

Non-federal cost share: Most Corps construction projects require a non-federal cost share ranging from 25% to 50% of project costs, depending on the project type. This is a significant local investment that must be committed before construction begins.

IIJA status: Nearly 70% of the Corps' IIJA funds went to construction, with 25% for operations and maintenance. FY2026, the last year of IIJA advance appropriations, ended September 30, 2026; check with your Corps district on the status of remaining IIJA-funded work.

Comparison: Which Program Is Right for Your Community?

ProgramBest ForProject SizeFunding TypeApply To
CWSRFWastewater, stormwaterAny sizeBelow-market loans; 49% as grants for disadvantagedState SRF
DWSRFDrinking water systemsAny sizeBelow-market loans; 49% as grants for disadvantagedState SRF
Lead pipe set-asideLead service line replacementAny sizeGrants/principal forgivenessState SRF
EC-SDCPFAS treatment (small/disadvantaged)Any size100% grants, no matchState drinking water agency
WIFIALarge water projects$20M+ ($5M small)Direct federal loansEPA headquarters
USDA Water/WasteRural communities (<10,000)VariesGrants + loansUSDA state office
IHS SFCTribal communitiesVariesConstruction programIHS Area Office
EPA Tribal Set-AsideTribal drinking/wastewaterVariesGrants (not loans)EPA directly
Army CorpsFlood control, navigationLarge-scaleFederal constructionCongressional authorization

How to Position Your Community for Water Funding

1. Get on Your State's Priority List

For SRF funding, you need to be on your state's Intended Use Plan priority list. Contact your state SRF program and ask about the next IUP cycle. Submit project information even if you're at the planning stage. Many states accept projects at varying stages of development.

2. Document Your Need

States rank projects using environmental and public health criteria. Compile:

  • Water quality data showing regulatory violations or contamination
  • Infrastructure condition assessments
  • Population and demographic data (disadvantaged community status helps significantly)
  • Health data linking your water issues to community health outcomes

3. Develop a Preliminary Engineering Report

Most programs require a preliminary engineering report (PER) evaluating alternatives, estimating costs, and recommending a preferred solution. This typically costs $50,000-$200,000 depending on project complexity. Some states provide technical assistance grants or SRF planning loans to cover PER costs.

4. Demonstrate Financial Capacity

Lenders (including SRF programs) need to see that your system can repay loans through user fees or other revenue. Prepare rate studies, financial projections, and documentation of your billing and collection system. Systems with very low user rates may need to demonstrate willingness to raise rates to support project debt service.

5. Act While IIJA Money Is Still Being Deployed

FY2026, which ended September 30, 2026, was the last year of IIJA advance appropriations. States will continue deploying already-allocated funds for years, but the size of future SRF capitalization grants depends on annual appropriations and is uncertain. If your community needs water infrastructure funding, the current moment represents an unusually large funding window that may not be replicated. Contact your state SRF program now.

For general guidance on federal grant compliance after you receive funding, see our federal grant compliance guide.


The State Priority List Backlog That Traps Communities With Real Need

The gap between federal funding availability and actual community-level disbursement is wider than the program websites suggest. Money obligated to state SRF programs can take years to reach local projects, because each state still has to rank, review, and commit funds project by project.

The pipeline from federal to state to local can clog when a state agency doesn't have enough engineers and compliance staff to process applications quickly. That's the bottleneck no one tells you about when you read the IIJA fact sheets.

The lead service line replacement funding has the same structural problem with an additional wrinkle. EPA revised its estimate of nationwide lead service lines downward from about 9 million to approximately 4 million in its 7th needs survey, based on improved inventory data from the Lead and Copper Rule Revisions requirement that water systems complete service line inventories. EPA used that survey for its FY2025 and FY2026 lead service line allotments, so state shares changed. If your state was expecting a specific allocation and the new allotment reduced it, your project's priority ranking may have shifted without any change in your community's actual need or the completeness of your application.

The state agency's internal capacity can matter more than federal funding levels. The IIJA delivered unprecedented water infrastructure money, but the program requires states to maintain updated Intended Use Plans, review preliminary engineering reports, conduct environmental reviews, assess financial capacity, and process binding commitments, all with state agency staff who often don't grow proportionally when federal funding increases. Several states have addressed this by hiring contract program administrators or partnering with state infrastructure financing authorities to process applications, but others are working through the same volume with the same headcount they had before IIJA. The communities that move fastest through the priority list are the ones that come in with completed engineering reports, clean financial documentation, and consistent contact with their state program coordinator. Don't wait for an invitation to check in. State program staff prioritize applications from communities that demonstrate they're ready to proceed.

The last IIJA appropriation year ended in September 2026, but the deadline that actually matters for your project isn't federal. It's your state's annual Intended Use Plan update cycle. In most states, that cycle closes 6 to 12 months before the state issues its funding commitments for the year. If you miss the IUP window, you wait another year regardless of how much federal money is sitting at the state level. Call your state SRF program coordinator this week and ask when the next IUP cycle opens and what documentation they need to add your project to the priority list.

What EPA's Water Infrastructure Pages Don't Tell You About Getting Funded

Water is one of the most complicated federal funding flows. Here's what the federal program websites don't prepare you for.

Your state's SRF program is the gatekeeper for most water funding, and each state runs it differently. Some states prioritize disadvantaged communities. Others prioritize shovel-ready projects. The scoring criteria vary so much that a project qualifying for principal forgiveness in one state might not rank high enough for a standard loan in an adjacent state. Contact your state SRF program before assuming you know how the money flows.

The "project priority list" is the real bottleneck. The IIJA added billions to the SRF, but money doesn't move to your community until you're on the state's project priority list. In several states, that list has a multi-year backlog. Communities that applied in FY2023 can still be waiting for a funding commitment, not because the money ran out but because the priority list queue didn't move fast enough. Get on the list early, and stay in contact with your state program coordinator.

Lead service line replacement funding has separate rules from regular DWSRF. The IIJA's $15 billion for lead pipe replacement has different terms (no state match, and 49% must go out as grants or principal forgiveness) and different eligible costs than standard DWSRF loans. Combining these funding streams in one application creates reporting and audit complications later. Keep them separate from the start.

Honest friction: the September 2026 end of IIJA appropriations doesn't mean the money is gone. You'll see warnings that IIJA water funding "expired" in September 2026. What ended was the last year of IIJA advance appropriations. States typically have two to four additional years to commit and spend SRF funds after receiving their federal capitalization grants. The deadline that matters for your community is your state's annual project priority list deadline, which varies by state and is usually 6-12 months before the state issues funding commitments.

WIFIA loans are unusually demanding for a loan program. EPA's WIFIA program offers low-cost loans for large projects, but the letter of interest, credit review, and full application take real staff time. WIFIA's best use is for projects over $50 million where the interest rate savings over a 35-year term genuinely justify the application effort. For projects under $20 million, the USDA rural programs or state SRF disadvantaged community set-asides are less competitive paths to the same outcome.

How Grantsights Checked This Guide

Source review by Grantsights: we checked EPA pages for water infrastructure funding (opens in a new tab), WIFIA (opens in a new tab), Clean Water SRF (opens in a new tab), Drinking Water SRF (opens in a new tab), USDA Water and Waste Disposal (opens in a new tab), IHS Sanitation Facilities Construction (opens in a new tab), Grants.gov (opens in a new tab) before this update. The practical gap is that water funding depends on state priority lists, disadvantaged community rules, loan forgiveness, and project readiness, not only federal program names.

Source checkedWhat it provesApplicant action
EPA SRF pagesClean water and drinking water funds flow through statesContact the state SRF office and get on the priority list
EPA WIFIALarge projects can seek direct federal credit assistanceUse WIFIA when project scale and credit capacity fit
USDA Water and Waste DisposalRural systems may have grant and loan routes outside SRFVerify population, rural status, rates, and income data
IHS DSFCTribal sanitation projects use a separate health and facilities routeConfirm tribal project inventory and sanitation deficiency status
Grants.gov and USASpending.govSome water funds are direct, but many are pass-through or loan-basedCheck recipient and assistance listing history

According to EPA (opens in a new tab), the Clean Water SRF is a state-run financing program for water quality projects. According to EPA (opens in a new tab), the Drinking Water SRF helps finance public drinking water infrastructure through state programs. According to EPA (opens in a new tab), WIFIA provides credit assistance for large water infrastructure projects. According to USDA Rural Development (opens in a new tab), rural water and waste disposal funding serves eligible rural communities and tribes.

Decision checklist: confirm state priority list status, project readiness, engineering report, environmental review, rate analysis, disadvantaged community status, match or loan capacity, and lead applicant before drafting. The fastest bad fit is a community chasing a direct federal grant when the real path is the state SRF or USDA field office. For example, a rural water district with a preliminary engineering report may fit USDA and SRF stacking, while a large regional treatment plant may need WIFIA credit support.

What Official Sources Don't Tell You

Official water pages explain programs, but they do not always show how local projects move from planning to priority lists to financing. The practical gap is project readiness: the winning path is often decided by engineering, rates, environmental review, and state ranking before the grant narrative is written.

Use the Grantsights database to compare live water infrastructure opportunities.

Sources

Frequently Asked Questions

How do State Revolving Funds work for water infrastructure?

State Revolving Funds are the primary federal mechanism for financing water infrastructure. EPA provides annual capitalization grants to each state, which the state matches at 20%. States then lend these funds to eligible borrowers, typically municipalities, water utilities, and special districts, at below-market interest rates (often 0% to 2%) with repayment terms up to 30 years. As borrowers repay loans, the money revolves back into the fund for new projects. There are two separate SRFs: the Clean Water SRF for wastewater and stormwater projects, and the Drinking Water SRF for drinking water systems. The Bipartisan Infrastructure Law added $11.7 billion each to the CWSRF and DWSRF over five years (FY2022-2026), plus $15 billion specifically for lead service line replacement. Under the BIL, 49% of supplemental SRF funds must be distributed as grants or principal forgiveness loans to disadvantaged communities, essentially converting half the program from loans to grants.

Who is eligible for water infrastructure grants?

Eligibility depends on the program. For SRFs, eligible borrowers include municipalities, counties, special districts, water and wastewater utilities (public and in some states private), and tribal communities. You apply to your state's SRF program, not to EPA. For USDA rural water grants, eligible applicants include public bodies (municipalities, counties, special-purpose districts), nonprofit organizations, and tribal nations serving rural areas with populations of 10,000 or fewer. For WIFIA loans, eligible borrowers include local governments, state infrastructure financing authorities, private entities, and public-private partnerships for projects exceeding $20 million ($5 million for small communities). For EPA's tribal programs, federally recognized tribes and tribal organizations are eligible. Army Corps of Engineers projects are typically congressionally authorized and don't follow a traditional grant application process.

What is WIFIA and how is it different from the SRF?

WIFIA (Water Infrastructure Finance and Innovation Act) is a federal loan program that provides direct, low-cost credit assistance from EPA to large water infrastructure projects. Unlike the SRF, which flows through states, WIFIA applicants deal directly with EPA headquarters. WIFIA can finance up to 49% of eligible project costs (80% for small communities), with repayment terms up to 35 years and deferral of up to 5 years after project completion. The minimum project size is $20 million for communities over 25,000 people and $5 million for smaller communities. EPA announced $6.5 billion in available WIFIA funding. WIFIA is designed for large-scale projects that may exceed what state SRF programs can handle, such as major treatment plant upgrades, regional pipeline systems, or large PFAS treatment facilities.

How much IIJA water funding is left and when does it expire?

The IIJA authorized $55 billion for water infrastructure over five years (FY2022-2026), making it the largest federal water investment in history. As of early 2026, EPA has distributed most annual SRF capitalization grants to states, but states are still deploying funds to local projects. FY2026 was the last year of IIJA advance appropriations, and that fiscal year ended September 30, 2026, so no further IIJA SRF tranches are scheduled. States typically have several additional years to commit and spend SRF funds after receiving their federal capitalization grants. For water specifically, most allocated funds have been committed to states, but communities should apply to their state SRF programs as soon as possible because state-level priority lists can shift and available funds are finite.

Is there federal funding for PFAS water treatment?

Yes. The IIJA created multiple funding streams for PFAS and emerging contaminants. The Emerging Contaminants in Small or Disadvantaged Communities grant program provides $1 billion per year for FY2022-2026 ($5 billion total) specifically for PFAS testing and treatment in communities on the frontlines of contamination. The CWSRF received an additional $1 billion over five years for emerging contaminants in wastewater systems. And both the regular CWSRF and DWSRF can fund PFAS treatment projects through their standard programs. The DWSRF also received a separate $4 billion over five years for emerging contaminants in drinking water. There's no cost-share requirement for the Small/Disadvantaged Communities grant. States administer these funds and distribute them non-competitively to eligible communities. Contact your state drinking water agency to access PFAS-specific funding.